Alger Elementary

Estimated Completion: Summer 2027

Location: 921 Alger St. SE

Architect: C2AE

Construction Manager: Owen-Ames-Kimball

Budget: $6.4 million

Funding Source: Reimagine GRPS with Us! Bond

Project Scope: Two new playgrounds, conversion of middle school spaces to elementary classrooms, HVAC and electrical upgrades, and refreshed interior finishes.


Construction Blog 

Posted 11/13/2026

Progress continues at Alger Elementary as the building transformation moves forward!

All interior demolition is now complete, and the interior rebuild is officially underway. Outside, work is also progressing on the two new playgrounds that will provide exciting spaces for scholars.

Posted 9/23/2026

Interior demolition is ongoing to prepare the former middle school spaces for elementary scholars next year.

Preparations are underway outside for the two new playground spaces.