Houseman Field

Estimated Completion: September 2025

Location: 162 Houseman Ave NE

Architect: C2AE

Construction Manager: Wolverine Construction

Budget: $5.1 million

Funding Source: Reimagine GRPS with Us! Bond

Project Scope: Renovation work will include playing turf replacement, running track replacement, field lighting upgrades, masonry restoration, and locker room acoustical improvements.

View presentation from Oct. 2024 community meeting

Community Events

Ribbon Cutting: To Be Determined

Community Information Meeting: October 16, 2024



Construction Blog

Posted 7/24/2025

Posted 7/15/2025

Check out this stunning aerial view of turf installation in progress at historic Houseman Field! The new field is already looking incredible. Next up is the track, with installation starting next week. 

Posted 7/10/2025

New Turf Coming Soon

Crews are currently prepping the field surface, with turf installation now underway. This upgrade will provide a high-quality, durable playing surface for our scholar-athletes and community events.

Track Replacement on the Horizon

A brand-new track surface is scheduled to begin installation on July 22. This upgrade will support safer, faster performances for our runners and improve the overall look and function of the field.

Restoring the Retaining Wall

The tuck-pointing work on the historic retaining wall is nearly complete, preserving an important feature of Houseman’s structure while ensuring long-term durability.

Parking Lot Progress

The new North Parking Lot is prepped and ready for paving, making access to the field smoother and more convenient for visitors and staff.

Posted 6/10/2025

Summer construction is rapidly kicking off at Houseman Field. The old turf and track have been removed. Work is now underway to prepare for the new turf and track to be installed.