Kent Hills Elementary is receiving air conditioning for the first time as part of a major investment in the northeast side elementary school. The project upgrades the old heating-only system to a heating, cooling and ventilation system. The work also includes new electrical and controls infrastructure to the new units.


Publish Date: January 11, 2024

The project is substantially complete. The cooling chiller is installed and will be started and commissioned in the spring of 2024. 


Publish Date: November 17, 2023

The project is substantially complete. The cooling chiller is installed and will be started and commissioned in spring 2024.

Kent Hills chiller


Publish Date: November 3, 2023

The new heating system is functional, being commissioned this week, and next week. The new chiller system will be installed on November 7 and commissioned in the spring. The substantial completion date for the project is November 30.

 


Publish Date: October 13, 2023

The anticipated ship date for the chiller unit is now Oct. 20. The unit will be installed as soon as it is delivered to the school. The project is still projected to be complete by mid-November.


Publish Date: September 29, 2023

The heating system scope is complete and the units are fully functional. Unfortunately, the delivery of the cooling unit was delayed until the end of October due to supply chain issues. The project is anticipated to be completed by mid-November.