The scope of the project includes upgrading the old HVAC units from heating-only to heating, cooling and ventilation units. This work also includes new electrical and controls infrastructure to the new units.
Publish Date: November 17, 2023
The project is substantially complete.
Publish Date: November 3, 2023
The project is substantially complete; the heating and cooling systems are functional and under the one-year guarantee period.
Publish Date: October 13, 2023
The construction project is substantially complete with final punch list items and a couple of warranty items expected to be completed by the end of October.
Publish Date: September 29, 2023
The construction project is substantially complete with final punch list items anticipated to be completed by mid-October. The project included installing new electric service, replacing the existing heating system, and providing a new cooling system.